Rapid slope protection at Newmont Ghana Gold Mine

Concrete Canvas® (CC) was specified as a solution for slope protection for slopes adjacent to the new reinforced earth wall at the Newmont Ghana Gold Limited (NGGL) site in Ahafo, Ghana. In addition to this CC was also used for the protection of earth wall footings and lining of slope toe drains for conveyance of slope runoff to the adjacent sump pump.

The length of the slope varied from 5m to 30m, while gradients were typically 1:1.5 but as steep as 1:1 in some areas. The toe drain measured approximately 2m wide in profile.
Stone pitching was originally planned for specification for the slope protection and toe drain lining.

Rapid installation
Concrete Canvas® can be installed with minimal plant requirement and with no back spray, debris or rebound associated with traditional concreting methods, reducing risks for contractors. The material is up to 10 times faster to install than alternatives, and can be installed with no requirement for specialist training, equipment or personnel, reducing time on site and costs. Furthermore, the rainy season in the Ahafo region of Ghana runs from April to August each year.

Wet weather friendly
The CC installation began in early March, making timely completion of this aspect of the project of paramount importance. CC can also be installed in wet weather conditions due to its 2-hour workability period following hydration. The nature of the site meant that continuance of works in the wet could be dangerous for installation crews working with conventional materials, like stone pitching.

Site preparation
As a result, CC was chosen in place of stone pitching. Prior to installation, all vegetation and sharp protruding rocks were removed from the slope profile. The slopes were then raked free of detritus material and voids filled with cement stabilised gravel. Anchor trenches measuring 300mm deep were excavated a metre behind the crest and at the toe of the slopes. These would later be used to capture the material edges before being backfilled to prevent water ingress below the material. In the drains, the profile was excavated according to capacity requirements. Longitudinal fall and shallow termination anchor trenches measuring 100mm deep were created adjacent to the drains for the capturing of material.

 

Learn more about slope stabilisation and erosion control at GEOTEX seminars

Our GEOTEX seminar programme for 2020 is now ready for registration in venues around the UK.
Learn more ……

No specialist equipment required
The specified bulk rolls of CC5™ and CC8™ were transported to site by Hiab crane and positioned behind the crest of the slopes for deployment. A standing frame-mounted spreader beam was used to deploy the CC, which was then cut to required length for installation in order to minimise wastage at the toe of the slope following deployment, or within the drain channel.

Layers of CC were installed with a minimum 100mm overlap. These overlaps were jointed using 30mm stainless steel screws at maximum intervals of 150mm. The material edges were secured within the anchor trenches through the overlaps with 300mm long galvanised steel pegs. On the slope face, additional anchor pegs, both barbed and galvanised, with nut fastened washers, were installed at 3,000mm spacing to all overlaps. CC was terminated against the RE Wall by pre-drilling and fastening at 100mm spacing with M8 mechanical anchors.

Simply hydrate the product
Following installation, CC was hydrated using pumped water from a 5,000 litre storage tank which was filled daily. Following initial hydration, CC was hydrated at 30-minute intervals a further three times to ensure sufficient saturation in the high temperatures experienced. All personnel working on the slopes were harnessed and used rope access for safe and secure installation of CC.

Maximised contractor productivity
Installation was completed over a 2-month period, inclusive of site preparation and changes to work sequencing. The area adjacent to the toe of the slopes was highly congested with other construction activities taking place, however, the contractor, Ropeak were still able to maximise productivity with installation in these challenging conditions.

A total success
The project has been deemed a success by both the client and consultant. None of the parties involved had used CC before, but were extremely happy with its ease of installation, suitability for the project requirements, safe handling capacity, speed of installation and costs. The CC installation project was completed on time, before the start of the rainy season, and with no injuries. A total of 9,000m² of CC5™ were installed on the slope, and a further 750m² of CC8™ within the drains.

OUR FREE TO ATTEND
SEMINAR SERIES

DEDICATED TO GROUND ENGINEERING

GEOTEX Portsmouth
TBC
*

GEOTEX Portsmouth

Fort Nelson
GEOTEX Leeds – AUG 26
August
26

GEOTEX Leeds – AUG 26

The Tetley Brewery
GEOTEX Birmingham – SEPT 9
Sept
9

GEOTEX Birmingham – SEPT 9

ThinkTank, Science Museum
GEOTEX Glasgow – SEPT 23
Sept
23

GEOTEX Glasgow – SEPT 23

Sir Chris Hoy Velodrome
GEOTEX London – OCT 14
Oct
14

GEOTEX London – OCT 14

RAF Museum Hendon
GEOTEX Bristol – NOV 11
NOV
11

GEOTEX Bristol – NOV 11

Bristol Zoo Pavillion
Share This